Client

NYSDOT

Location

Westchester County, NY

Completion Date

2004

Markets

Government, Transportation

Division

Engineering

Discipline

Construction Management, Structural Engineering, Traffic Engineering

Boswell provided construction inspection services for the full reconstruction and realignment of 5.7 kilometers on the Hutchinson River Parkway (HRP) between Interstate I-287 and the Connecticut state line.

Work on this A&B type bid project (contractor incentives) also included superpave asphalt concrete; crack and seal existing concrete pavement with asphalt overlay; stone masonry retaining wall construction; soil nail wall construction; precast T-wall construction; precast concrete noise barrier wall construction; extension/replacement of six large precast concrete culverts; utility work; traffic signals; wetland mitigation; widening of three existing reinforced concrete arch bridges to provide additional lanes; replacement of the existing bridge over the HRP with a new reinforced concrete arch bridge, while maintaining traffic on a temporary bridge during the construction.