FirstEnergy 230kV Loop Tap to PSE&G Hopewell Substation
Project Information
• Installed 2 drill shaft foundations and erected 2 steel sectional monopoles.
• Pulled new conductor for tie-in to new PSE&G Hopewell substation.
• Pulled optical ground wire through dead ends into substation.
• Work included guard structures, traffic control and a NJDOT permit for the crossing over NJ Route 31.