Deep Run Substation 115-34.5kV Transformer Replacement
Project Information
• Removed existing and installed new 115-34.5kV 150MVA transformer.
• Installed new 230kV circuit switcher and SF6 gas circuit breaker.
• Constructed new below grade foundations, transformer pad and containment.
• Installed new wiring and relays in existing control house.